Project Milestones
From concept to construction - a transparent development path
Completed (2024-2025)
Pre-feasibility (INTEC, Germany)
Site selection
Off-takers identified
120 MW Wind PP interconnection secured
PDA programme (Roland Berger, Clean Hydrogen Partnership)
McKinsey research
Community engagement programme
CEHC membership
In Progress (2025-2026)
Pre-FEED stage for PtX
36 MW Wind PP under construction. COD - Q4 2027
120 MW Wind PP. RTB - Q4 2026; COD - Q4 2028
Strategic investor/off-taker engagement
Consortium set-up
Upcoming (2027-2032+)
FEED & FID
Financial Close
Construction phase
First renewable H2: 2029
Phased expansion through 2033
Independent Validation
Bankability confirmed by recognised European institutions
GreenWest PtX has completed formal validation by three key institutions in the European hydrogen ecosystem.

European Commission Investment Framework Recognition
Selected for engagement under the European Commission's Ukraine Investment Framework Call for Expressions of Interest.

Clean Hydrogen Partnership
Project concept, setup, and bankability confirmed through the independent PDA+ programme review process.

CEHC Membership
Central European Hydrogen Corridor membership confirmed with executed MoU.

Climate Innovation Vouchers
Additional institutional support received through European Climate Innovation Voucher programme.